Dulas delivers 250kW Llys y Fran hydro scheme

Renewable energy consultancy Dulas has announced the completion of a 250kW hydro- electric scheme at Welsh Water's Llys y Fran reservoir.

Llys y Fran reservoir is in PembrokeshireLlys y Fran reservoir is in Pembrokeshire

The scheme, located in a Pembrokeshire country park, controls the flow release to the river Syfynwy to support abstraction at a pumping station located some 15km downstream.

Commissioned in September 2017, the scheme is already approaching 1 million kWh of generated electricity, and will power a planned visitor centre, activity hub and boathouse, as well as exporting energy to the National Grid.

Hydro-electricity has long contributed to Wales’ renewable energy mix, with more than 275 projects located across the region, and the Welsh Government recently announced a new grant scheme that offers 100 per cent relief on business rates for community schemes with a rateable value of up to £50,000.

Equally, and as UK Feed-in Tariffs continue to be phased out, existing reservoir sites can offer opportunities for the UK to continue to build out its hydro capacity.

Llys y Fran is a raw water storage reservoir, with a capacity of nearly 10,500 Ml. Dulas was appointed EPC contractor by Welsh Water for the project, and was charged with the design, procurement, installation and commissioning of the hydro generator before it was handed over to Welsh Water.

Preliminary work at the site saw Dulas design and install a raw water supply line from one of the discharge regulators along the front of the valve house, requiring the construction of three concrete pillars for support. The main works comprised the installation of a new 250kW hydro turbine and generator, and construction of a new power house building, discharge pipes and an automatic failsafe bypass valve and pipework.

In addition, Dulas added a telemetry function that enables remote control of the new turbine and its bypass system, as well as control of the reservoir spill to within 25mm.

“Dulas has long been a trusted supplier to Welsh Water, and our team has significant experience in the optimisation of existing reservoirs and hydro infrastructure to fully develop their renewable energy potential,” Crispin Angood, senior project manager at Dulas, said.

“While the decline of Feed-in Tariffs will present severe challenges for the sector across the UK, schemes like that at Llys y Fran demonstrate the potential of  reservoir and water treatment facilities to boost generation by incorporating hydropower technology.”

“Having worked with Dulas on a number of our other operational hydro schemes, we were confident in their ability to maximize energy generation from the reservoir,” Mike Pedley, head of energy at Welsh Water, said.

“The team once again delivered to a very high standard and, as the site is located within a country park, it will serve as a showcase to educate the public on how a hydro scheme operates.”

Author: Robin Hackett, editor, WWT
Topic: Energy/Water Nexus
Tags: hydro electricity , reservoir , Contractor , Dwr Cymru Welsh Water

Newsletter

Sign up today for your daily news alert and weekly roundup

© Faversham House Group Ltd 2019. WWT and WET News news articles may be copied or forwarded for individual use only. No other reproduction or distribution is permitted without prior written consent.

Cookie Policy   |   Privacy Policy