• Sign Up or Sign In

Project Focus: UU opts for mega-tank in Mersey project

As part of a major programme to protect the River Mersey from CSO discharges, United Utilities has built a giant precast detention tank at Widnes which is 140 metres in length

The giant precast concrete tank is 140 metres in lengthThe giant precast concrete tank is 140 metres in length

The Mersey has never been known for being the cleanest of England’s rivers: in the mid-1980s, the Mersey Estuary was declared the most polluted estuary in the UK. But today it is cleaner than it has been for more than a century, and a series of projects from United Utilities is about to improve matters still further.

UU is currently undertaking a massive programme of work to improve wastewater treatment and the sewer network in the Mersey catchment area. This includes an ambitious £200M extension (now nearing completion) to Liverpool’s wastewater treatment works at Sandon Dock.

But further upstream other, equally impressive, improvement work is also underway. United Utilities and its framework contractor KMI (a joint venture between Kier Infrastructure, J Murphy & Sons, Interserve Construction and consulting engineer Mouchel) are currently engaged in several large scale engineering works, not least the installation of what it believed to be the largest pre-cast concrete detention tank ever seen in England.

United Utilities project manager Eric Hepworth says: “The detention tank is being built just off the Knowsley Expressway, in Widnes, and will vastly increase the capacity of the local sewer for safely retaining storm water, which might otherwise ended up flowing into the river Mersey via Ditton Brook.”

The rectangular detention tank will measure 140m by 43m – covering a substantially bigger area than a football pitch - and will be capable of storing the equivalent of 36 million pints of water.

“Over the past few years we’ve created extra storm storage in our sewer network across the Merseyside area. This will help improve the River Mersey by reducing the number of times the local sewer system overflows in heavy rains,” says Hepworth.

The project – officially known as the HAL0037 Ash Lane UID (unsatisfactory intermittent discharge) scheme – is one of a number of jobs associated with the overall AMP5 Change Protocol C (CPC) Knowsley, Huyton and Widnes (KHW) programme of works.

Besides HAL0037, the AMP5 KHW CPC Catchment UID programme also included another six jobs, five of which, now complete, comprised Phase 1. Phase 2 comprises construction of 23,500 cubic metres of additional storm storage at Huyton WwTW, now also complete, leaving the Ash Lane UID as the last scheme to be delivered in the KHW programme.

Temporary storage flow

The existing Ash Lane CSO is a stilling pond type located in a field adjacent to Ash Lane, Widnes. During heavy rainfall, spill flows discharge through a 1,750mm diameter pipe to Ditton Brook, about 680m downstream of the chamber. There is currently no storage at the site and so flows pass through the CSO chamber and over a spill weir into the watercourse.

The aim of the current project is to provide a means of storing these flows temporarily and allowing silt and other contaminants to settle before the clean water is discharged under controlled conditions.

Work started with tree removal and the erection of newt fencing in January 2014 and continued with construction of a new site access road in October. The project is set to be completed this month (September 2015).

The original scope of the project was to have two CSO screens capable of screening up to 2,800 litres/sec each to 6mm in two dimensions. The new detention tank would have 17,000 cubic metres of storage and an integral flushing system to clean the tank on emptying. The tank itself was envisaged as two 35m diameter diaphragm wall structures each about 20m deep.

A set of duty/standby storm return pumps would return flows downstream of the new CSO chamber once storm flows subsided while a smaller “scavenger” pump was to be provided within the detention tank so that the tank could be fully drained.

Building such large structures on site is time-consuming and vulnerable to delays due to poor weather. Additionally, there was a potential risk of flotation of the detention tank due to upward ground and water pressure.

Various options were considered – including using thicker walls and floors and pinning the structure down with anchor piles.

But after an extensive value engineering exercise by KMI, an alternative design employing a single detention tank assembled using precast concrete components was chosen. This avoided the flotation problems by using a shallower tank that covered a much larger footprint.

“The contractor tendered to three or four companies and chose a solution put forward by Kijlstra,” says Eric.
Kijlstra, whose headquarters are in the Netherlands, is a relative newcomer to the UK; earlier this year it opened its first UK factory in Henlade, Somerset. As a supplier of precast concrete products to the water industry, it has aimed to change perceptions in the civil engineering and utilities sector with time and cost-saving designs.

Off-site solution

Kijlstra’s off-site solutions ticked all the right boxes for United Utilities, says Hepworth. “We have a ‘design for manufacture’ strategy at United Utilities and a team that is constantly looking for innovative solutions,” he explains. “This includes, but is by no means confined to, precast concrete. Off-site manufacture cuts the amount of work done on site, which is safer and quicker, and quality and finish is also much better because it’s made in factory conditions”.

The tank is truly monumental in scale: buried under 3m of soil, is has internal dimensions of 135m x 42.1m x 3m high. It has an in-situ base set at a fall of 1:200 and is divided internally into eight 5m-wide channels which are easily cleaned by the flushing mechanism.

The external walls are assembled using Kijlstra’s precast concrete panels measuring 6m wide and 300mm thick. The roof comprises panels measuring 5m x 3m and also 300mm thick, with an additional 200mm thick layer of insitu concrete on top.

Kijlstra also supplied the precast CSO chamber and return pumping station along with the tank itself. “One of the innovations that impressed the client was that we presented to them with the flushing system partially factory-fitted,” says Kijlstra’s project manager Steve Gainsley.

When in use, the tank will start collecting excess flows when the rate exceeds 274 litres/sec. The flow is screened and spills into the pumping station from where it spills in sequence into the flushing chambers at the top of the detention tank.

When the flushing chambers are full, the flow spills over the weir in the pumping station and down to the bottom end of the tank which then fills until the storage volume is reached. At this point the spill weir level in the CSO chamber is reached and the flows discharge to the existing overflow pipe into Ditton Brook.
The considerable volume of soil excavated to accommodate the tank is being re-used on site for landscaping purposes.

For Eric Hepworth, who has 40 years’ experience in the water industry, the use of precast concrete for this type of structure continues an ongoing trend in the industry.

“I’ve worked with precast concrete many times before – it’s not new,” he says. “But the biggest change I’ve seen in the industry is a massive improvement in health, safety and welfare. Offsite construction is much safer and I think that’s driving the trend. Precast has always been there, but this takes it to a new level.”

Topic: Sewer Networks , Flooding & Urban Drainage
Tags: United Utilities , tanks

Newsletter

Sign up today for your daily news alert and weekly roundup

© Faversham House Group Ltd 2019. WWT and WET News news articles may be copied or forwarded for individual use only. No other reproduction or distribution is permitted without prior written consent.

Cookie Policy   |   Privacy Policy